County says Justice Building repairs delayed until Spring

Staff Report

WARSAW — Repairs to the Kosciusko County Justice Building won’t happen until next spring.

An entryway on Lake Street was heavily damaged in August of 2025 when a limestone slab came crashing down from above a public exit, which still remains closed.

While some of the preliminary work will be done over the winter, County Commissioner Cary Groninger says the contractor plans to wait until spring to do much of the work.

Some of the decision has to do with the materials that will be involved in the project.

The original damage led to a large-scale assessment of the building, which led to the discovery of numerous potential weaknesses in older parts of the building.
The county in July hired Structural Waterproofing and Restoration to make the repairs at an estimated cost of $698,000.

The post County says Justice Building repairs delayed until Spring appeared first on News Now Warsaw.